Figure 2From “Implementation backlog: delivery capacity governs new sales”

Implementation backlog clearance horizon

For the same implementation backlog, less available delivery capacity extends the approximate backlog clearance horizon.

Cite Embed

Figure 2Implementation backlog clearance horizon

Chosen scenarioOngoing work (hours/month)Free capacity (hours/month)CalculationApproximate backlog clearance horizon (months)
Larger reservation1,6002,40013,440 / 2,4005.60
Opening scenario8003,20013,440 / 3,2004.20
No ongoing-work reservation04,00013,440 / 4,0003.36

Swipe or scroll horizontally if the table is wider than your screen.

Source: Author-created arithmetic: B = 13,440 hours divided by (4,000 usable hours/month minus ongoing-work hours/month). No simulation, empirical churn curve or source-derived thresholds

PNG4:3, 1600 × 1200, with the title, the source line and the attribution set in the image isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02.png

Source and evidence

Each line names a claim related to this exhibit, its source, and how it was checked.

  • B V01BACK-OWN-C1 B = U/C is a dated approximate workload-clearance horizon in months, where U is committed unstarted hours and C hours/month available after reservationsAuthor formulation; units and assumptions are stated in the article
  • B V01BACK-OWN-C6 All article scenario numbers are constructed by the author, with specified units and assumptions, not observed outcomes or simulationsAuthor-created examples; no client data or empirical estimates

Grades: A, verified against the printed page of the primary source · B, primary source, text layer only · C, authoritative secondary · D, reported.

Cite or embed

APA 7

Isoglu, S. (2026). Implementation backlog clearance horizon [Figure]. isoglu.com. https://isoglu.com/insights/exhibits/isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02/

BibTeX
@misc{isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02,
  author = {Isoglu, Sinan},
  title = {{Implementation backlog clearance horizon}},
  year = {2026},
  howpublished = {Figure 2, isoglu.com},
  url = {https://isoglu.com/insights/exhibits/isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02/},
  note = {From the essay {Implementation backlog: delivery capacity governs new sales}}
}
Embed this exhibit

Copy this HTML to use the PNG exhibit on your site with its source line and a link back to the exhibit page.

<figure>
  <a href="https://isoglu.com/insights/exhibits/isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02/">
    <img src="https://isoglu.com/social/isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02.png" alt="Figure 2: Implementation backlog clearance horizon" width="3200" height="2400">
  </a>
  <figcaption>Figure 2: Implementation backlog clearance horizon. Source: Author-created arithmetic: B = 13,440 hours divided by (4,000 usable hours/month minus ongoing-work hours/month). No simulation, empirical churn curve or source-derived thresholds. <a href="https://isoglu.com/insights/exhibits/isoglu-2026-implementation-backlog-is-a-delivery-capacity-constraint-fig02/">View exhibit</a>.</figcaption>
</figure>